top of page

.02

UNKI PLATINUM

AC FURNACE

PROJECT TITLE:

UNKI PGM Smelter

LOCATION:

Shurugwi, Zimbabwe

 

PROJECT METRICS:

14,000 TPA matte production from 62,000 TPA dry  concentrate feed

 

DURATION:

18 months

 

CLIENT:

Anglo American Platinum

 

CONTRACT TYPE:

EPCM

 

DESCRIPTION:

Greenfield smelter operation at the UNKI mine and concentrator site.

 

MAIN PROJECT SYSTEMS:

  • 3 Electrode AC shielded arc closed furnace.

  • Electrostatic precipitator.

  • Slag granulation.

  • Pneumatic transfer systems.

  • Flash dryer.

  • Closed circuit cooling water system with evaporative coolers.

  • Product crushing and screening plant.

  • Slag stockpile.

bottom of page